Demand Response

New York ISO


The New York Independent System Operator (NYISO) manages New York's electricity transmission grid - a 10,775-mile network of high-voltage lines that carry electricity throughout the state. The NYISO is responsible for keeping power flowing to 19.2 million New Yorkers. The state's geographic location also means that the NYISO serves as the pivot point for the transfer of electricity to and from the northeastern U.S. and Canada.

Economic Programs

The NYISO's Day-Ahead Demand Response Program (DADRP) allows qualifying customers to bid their load reductions into the Day-Ahead energy market as generators do. Offers determined to be economic are paid at the market clearing price. There is a 1MW threshold for participation, and standby generators are not allowed in this program. Customer loads that clear in the Day-Ahead market are firmly committed during the hours that cleared.

Reliability Programs

Special Case Resources (SCR) is a program that pays qualifying customers a capacity payment for their reducible load whether an event is called or not. The customers must, as part of their agreement, curtail power usage when asked by the NYISO. The customer will have 2 hours notice to reduce its load by contracted levels, with a warning usually being issued the day before an anticipated emergency event. Customers are paid a capacity payment based on the ICAP market price for providing their load. Those that do not provide their contracted capacity during an emergency event will see their payments reduced.

To learn more about New York Demand Response programs click here.

Program Summary

NYISO ProgramICAP Special Case Resource (Reliability)Day Ahead (Economic)
Minimum 100 kW 100 kW
Notification 21-hour notice As bid
Interruption Length Minimum 4-hour blocks Minimum 4-hour contiguous blocks determined by customer
Capacity Payment Yes No
Energy Payment Greater of Real Time LBMP or $500/MWh Day ahead LBMP or bid price
Payment Trigger When enrolled; energy payment when event called. When bid accepted
Payment Schedule Within 30 days of receipt of payment.
Equipment IDR IDR

request a quote
customer login
A world-class lineage
We're part of GDF SUEZ - a leading international company.
 Company Structure
Demonstrable success
We solve energy problems - see how we've done it.
 Case Studies